|
Wyneken Expansion News: |
|
|
|
|
| Phase II Construction and Remodeling Begins! | |
| July 1, 2003 | June 18, 2003 |
| May 2003 |
Bleacher
Construction: March-April 2003 |
| January 7, 2003 | December 4, 2002 |
| November 15 & 18, 2002 | November 1, 2002 |
| September 25, 2002 | September 5, 2002 |
| August 15, 2002 | July 15, 2002 |
| June 29, 2002 | June 2002 |
| May 2002 | March-April 2002 |
|
SUNDAY, MARCH 3, 2002: Groundbreaking ceremonies took place today, with
nearly 200 members of the Wyneken community attending. The rite of
groundbreaking was led by Pastors Brege, Dahling, and Olson of our three
churches. Several people brought shovels along to participate in the
first dig. Coverage of the event was found within the Decatur Daily
Democrat and on WPTA TV 21 Alive.
To prepare for construction, several trees were removed last week and
the old storage garage/shop class was burned down on March 2nd. The next
step is moving the gas line during the week of March 4th. Click here to see groundbreaking pictures. Click here to see panoramic photos of groundbreaking. Click here to see March 2002 construction progress. |
|
|
Phase 2 construction will be based upon available funding. It would include renovation of the existing offices, kitchen/lunchroom, and upper grade restrooms. This phase is slated to begin in Summer 2002. |
|
|
AUGUST 2001
UPDATE: This month, we... * Finalized floor plans for state and local approval by the architect, Ken Nord of CE&M, Inc. * Soil testing is being completed for the septic system design. * Storm water detention areas are being planned. * The gym size, ten feet wider than previously shown, will allow bleacher seating on both sides, and two practice courts will fit crosswise. * A development plan hearing with the Adams County Planning Commission is scheduled for September. * A construction schedule will be developed as progress is made on the plans, with most likely spring construction and fall site work possible. |
|
| IN SUMMER 2001, Wyneken volunteers started preparing the building site for next year's construction. The playground equipment was removed in mid-June for relocation away from the future building area. This will hopefully establish a new playground area that need not be moved again. On Saturday, July 7th, the two modular classrooms were moved from the north end of school to the front of the upper grades building. This will enable these rooms to be free of future construction noise and dust. During this year, Randy Everett will excavate the site, allowing the ground to settle before laying the foundation. | |
| THE LUTHERAN FOUNDATION of Fort Wayne, Indiana has given the Association its second matching grant to date. It has given $100,000 for each of the three congregations to match. The overall project costs are currently just under $2,000,000. With the matches, our building fund will make the $1,000,000 mark. Thanks be to God for all the blessings He has given this project! | |
| THE FACULTY OF WYNEKEN has decided to adopt its 2001-2002 school year theme with our construction project in mind. Our new theme will be "Christ Is Our Cornerstone". | |
|
AN UPDATE FROM MAY 2001: The Wyneken Building Committee wishes to give an update on the progress of the building expansion program. The committee has been meeting since February 2001 and the members include: St. John’s - Leroy Hartman, Fred Sauer, Ron Fuhrmann (Chairman); St. Paul’s - Mike Fruchte, Thomas Korte, Alan Zimmerman; Zion Friedheim - Randy Everett, Jim Crosby, Mike Werling (Secretary). The accomplishments made thus far include: Finalizing a floor plan to obtain state and local building permits, interviewing and selecting the architectural/engineering firm of CE & M Inc., (Ken Nord), removing and storing bleachers from Bellmont High School for use in our new gym, and planning a new septic system. The outside modular classrooms will be relocated this summer to accommodate both student use for next fall and building site preparation. A construction schedule will be finalized as the project proceeds. They anticipate beginning site preparation work this fall, and construction in Spring of 2002. Herman Linnemeier and Jim Crosby have volunteered to be the project managers representing Wyneken School Association. |
|
|
NEWS FROM FEBRUARY 11, 2001 The current sketch,
popularly known as "Plan B", features an addition of six
classrooms. Currently, three classes meet outside of the Wyneken
structure. The 5th grade and 1st/2nd grade split class meet in adjoining
modular buildings, while the pre-kindergarten meets off campus at Zion
Lutheran Church (Friedheim). This expansion will reunite our campus for
the first time since early 1997. |
|
|
News from December, 2000 The pledge drive is still on, with an end date of December 31st, 2000. At that time, all monies pledged will represent 65% of the building project cost. Right now, our goal is to have $1,300,000 pledged (65% of the $2,000,000 cost). There are a few weeks left for pledge cards to be turned into your churches. Please consider giving to this project. The goals and hopes, God willing, will be the break ground in Spring 2001.
|
|
|
|
|
This plan features six additional classrooms, located at the northern part of the campus. Four will house classrooms which currently are in modular buildings (1st/2nd grade and Mrs. Nichols' 5th grade), undersized (resource room), or off-campus (pre kindergarten). The additional classrooms will be used for specific classes (like music and art) until they are needed for school growth. A high-school sized gymnasium is being added to the northeast corner of the school. The old gym will be partitioned to form a larger lunchroom and a "multi-purpose" room. The office will be moved to the west side of the building, and a new parking lot will be placed there. The old offices, lunchroom and resource room will be remodeled to meet current spacing needs. |
|
| ©2003, Wyneken Memorial Lutheran School. | |